Project Status Update

End of Sprint 3

Date: 11/19/2024

Major Project Feature Summary:

Feature Status Progress
Ensure Cross-Platform Functionality 🟢 100%
Implement User Preferences Feature 🟢 100%
Platform-Specific Testing and Bug Resolution 🟢 100%
Backend Integration for User Preferences 🟢 100%
User Preferences Testing 🟢 100%

Current Project Status: GREEN

The project status is now GREEN as we have successfully completed all planned features for Sprint 3. Cross-platform functionality, User Preferences integration, and platform-specific testing have been finalized. Bugs identified during testing have been resolved, ensuring a consistent user experience across Android and iOS.

Team Goals for the Upcoming Sprint:

  1. Begin user testing to gather feedback on User Preferences functionality and cross-platform performance.
  2. Focus on enhancing performance and further optimization based on feedback.
  3. Prepare for upcoming integration of advanced trip-planning features.

Individual Team Member Status:

  • 1deeppanwala:

    • Completed: Finalized UI and resolved minor bugs in User Preferences, contributed to successful platform-specific testing.
    • Next Sprint: Focus on UI refinements and support user testing feedback analysis.
  • Pavanrohith25:

    • Completed: Completed Firebase integration and enhanced cross-platform optimizations.
    • Next Sprint: Assist with data collection for user feedback on cross-platform performance and User Preferences feature.
  • HiteshNaval:

    • Completed: Finalized backend setup for User Preferences and conducted backend testing for data persistence and performance.
    • Next Sprint: Review user feedback on backend performance and make adjustments as needed.
  • PurveshKapadiya:

    • Completed: Led platform compatibility testing and resolved Android-specific bugs, ensured consistent experience across devices.
    • Next Sprint: Collaborate on performance enhancement based on user testing results.
  • bnevimal3:

    • Completed: Completed backend linking and User Preferences UI elements, supported testing and issue resolution.
    • Next Sprint: Analyze user feedback on the UI and implement adjustments based on feedback.

Team Activities:

  • Sprint 3 Retrospective Meeting: Reviewed sprint successes and areas for improvement (11/18/2024, all members).
  • Testing and Bug Fixing Sessions: Intensive bug resolution and testing sessions on cross-platform functionality, led by PurveshKapadiya and 1deeppanwala.

Team Project Decisions:

  • Concluded that performance optimization will be a major focus in the next sprint to enhance user experience.

Other Comments:

No additional comments at