Week 8: Happy Thanksgiving - 18F/noaa-nwm-pa GitHub Wiki

Hi all, Peter and Andrew were onsite at the National Water Center in Tuscaloosa last week and we learned a lot from our sessions on Tuesday and from listening in on Wednesday.

We loved the depth of participation in Friday’s Sprint Demo. We’re attaching the slide desk (as presented) and the list of consensus hypotheses that we generated. Let us know if you spot a difference between your notes and what’s listed! Do so by email, or as an issue on the GitHub version: https://github.com/18F/noaa-nwm-pa/blob/master/hypotheses.md

As you know, it’s Thanksgiving week. Peter and Andrew are working short weeks, then gearing up for a final week of report writing.

Last week

  • Solidified next steps for the NWM software architecture approach
  • Held onsite sessions in Tuscaloosa
  • Completed data extraction from interviews and continued theme identification
  • Held demo meeting on Friday

Next up

  • Preparing a working draft of our report
  • Sharing draft for feedback

By the numbers

Last week we billed a total of $21,380. There is currently $46,116 remaining on this project which leaves us on track for a 12/6 end date.

Project timeline week 8

Thanks,

  • Kathryn, Peter, Andrew, and Mark