Revise GSIP voting process to assuming a +0 vote after 10 days.
Jody Garnett, based on GeoServer meeting discussion.
This proposal is for GeoServer 2.17.
- Under Discussion
- In Progress
- Completed
- Rejected
- Deferred
Our current proposal process sets a 7 day limit on voting, resulting in votes being trapped in limbo for lack of feedback.
Propose revising GSIP voting process to assuming a +0 vote after 10 days (similar to the GeoTools community policy).
n/a
Some confusion/discussion on the email list resulted in a debate between 14 days (two weeks) and the shorter 10 days. The majority were in favour of a 10 day period.
Project Steering Committee:
- Alessio Fabiani: +1
- Andrea Aime: +1
- Ian Turton: +1
- Jody Garnett: +1
- Jukka Rahkonen: +1
- Kevin Smith:
- Simone Giannecchini: +1
- Torben Barsballe: +1
- Nuno Oliveira: +1 for 10 days