I'm working on the Phase 6a scope based on phase 6 scoping discussion here.
Schedule:
Planning on two-zone system in June and three-zone / TVPB in August. Jeff on vacation in July.
I'm working on Phase 6 SOW, strategic plan, and documentation/tidying up in June.
I'm out the following week so cancel 19th meeting. No other major vacations planned.
Project progress:
~60% of project budget spent so ~$110k remaining
Major work left - strategic development plan, two-zone systems, three zones / TVPB
Once example distribution feature working, will ask for review of new notebooks, documentation, estimation mode related contributions
Have overspent estimation mode by $10k with some remaining documentation to do. Performance tuning task is $35k and we discussed using some (or all) of it for estimation mode. I suggest we wait until we get closer to finishing two and three zones to decide.
Strategic development plan draft document should be a good solid draft.