Project Meeting 2016.06.15 - ActivitySim/activitysim GitHub Wiki

Logging and Tracing

  • Logging and tracing are now implemented and we will review an example during the meeting
  • For the trace HH, every data table - chooser, expressions/utilities, probabilities, choices, etc. - is written out to CSV file
  • The order of trace output files is written to a master trace file
  • Tests will be implemented by Friday
  • Also fixed a bug so small sample sizes can now be run
  • Add to issue some ideas for improvements
  • Fix a couple small items that will be added to the issue as well

Next Steps

  • Update all documentation for previous commits + logging and tracing
  • Return to debugging/fixing the existing code for a full model run? (see below)

Project Admin

  • We have delivered everything scoped + more for task 2 and task 3 and are just about done with task 9
  • We have spent the entire budget for tasks 2, 3, and 9 as well
  • We should return to debugging/fixing the existing code for a full model run but we don't have a task for this so can we re-allocate funds from other tasks?
  • Skim handling is basically done, but we can't really confirm until we fix the inherited issues
  • Can these issues be dealt with under the Nested Logit task for example? @bstabler: A bit, but we could implement a nested logit model without dealing with these inherited issues. It doesn't make a lot of sense to build upon a platform with these issues; let's correct the problems and then move forward
  • MPO partners not surprised but need to discuss and get back to us
  • Three options to consider: 1) add funding, 2) swap new task for existing tasks, 3) ignore and move forward with scoped tasks
  • RSG will work on finishing tracing and updating documentation in the meantime
  • Project schedule is fine
  • MPO partners will also discuss their plan for next year as well
  • Agreement with AMPO valid through June 2017
  • Jeff will be half-time for the next two months while he vacations/works in France