Fix a couple small items that will be added to the issue as well
Next Steps
Update all documentation for previous commits + logging and tracing
Return to debugging/fixing the existing code for a full model run? (see below)
Project Admin
We have delivered everything scoped + more for task 2 and task 3 and are just about done with task 9
We have spent the entire budget for tasks 2, 3, and 9 as well
We should return to debugging/fixing the existing code for a full model run but we don't have a task for this so can we re-allocate funds from other tasks?
Skim handling is basically done, but we can't really confirm until we fix the inherited issues
Can these issues be dealt with under the Nested Logit task for example? @bstabler: A bit, but we could implement a nested logit model without dealing with these inherited issues. It doesn't make a lot of sense to build upon a platform with these issues; let's correct the problems and then move forward
MPO partners not surprised but need to discuss and get back to us
Three options to consider: 1) add funding, 2) swap new task for existing tasks, 3) ignore and move forward with scoped tasks
RSG will work on finishing tracing and updating documentation in the meantime
Project schedule is fine
MPO partners will also discuss their plan for next year as well
Agreement with AMPO valid through June 2017
Jeff will be half-time for the next two months while he vacations/works in France